 Projects can be easily created and managed at a single Project workspace. Only project members would have permissions to view the workspace. All project documents can be stored and all project-related communication can be centrally managed and archived within the project workspace.
Project Plan  The main highlights of the project plan are:
- The first week would be spent on requirement analysis. The project manager and implementation team would go over all the described requirements in detail to ensure we have understood the requirements and gauge the impact, if any, on the project plan.
- About 4 weeks have been estimated for the entire UI design and review. At the end of the 4th week, the UI should be frozen.
- Portal installation would happen in 2 phases the development environment would be ready in the first week while the production environment would be made ready between the 8th and 10th week.
- All custom development and integration with existing systems will be done in the development environment between the 2nd and 9th week.
- The 14th week will be preparation for go-live. All final tests will be performed to ensure system can go-live.
Task List
|
Priority
|
Task
|
Status
|
Due date
|
% Complete
|
Category
|
Owner
|
Comments
|
1- High |
Develop Demo |
Complete |
7/25 |
100% |
Sales Tools |
Len |
|
1- High |
Update web site |
In progress |
8/1 |
80% |
Promotion |
Len |
update product section |
2- Medium |
Update Product Overview |
In progress |
8/4 |
75% |
Promotion |
John |
|
2- Meduim |
Review New Name with Legal |
In progress |
7/28 |
80% |
Legal |
Tamara |
|
PSR Meeting Minutes (7/20/06)
- John to update product overview by 8/4
- Tamara to review new name with legal by 7/28
- Len to update product section on the site 8/1